[I]
[J]
[K]
[L]
[M]
[N]
[O]
[A-D]
[E-H]
[P-Q]
[R-Z]
[Home]
- Implementer
- This role
assists the project manager in designing a workable plan, and then implementing
the plan by doing the work.
- Indirect costs
- Expenditures that are not
necessarily due to the activity itself.
- Individual commitment
- It is determined
by dividing an activity's individual effort estimate by its total duration.
- Individual effort
- The effort each person will contribute to the activity.
- Initiating
- The first of the five processes of project
management. Initiating sets the foundation for the entire project. The
PMBOK® Guide defines
initiating as the process of recognizing that a project should begin and
committing to do so.
- Integration management
- According to the PMBOK® Guide ,
project integration management includes the processes required to ensure that
the various elements of the project are properly coordinated.
- Internal Rate of
Return (IRR)
- The rate of return implied in the project. It is the rate that
would make the NPV equal to 0. This calculation assumes that cash flow from the
project will be reinvested at the same rate of return as that of the project.
- Just in time (JIT) scheduling
- see ALAP scheduling
- Knowledge areas
- According to the
PMBOK® Guide, the nine areas that describe project management
in terms of its component processes. The nine areas consist of: scope
management, time management, human resource management, procurement
management, cost management, risk management, communications management,
quality management, and integration management.
[top]
- Lag
- A time delay before the successor activity can start. Also
referred to as a gap.
- Late finish (LF)
- The latest an activity can finish
without delaying project completion based on the end date.
- Late start (LS)
- The latest an activity can start without delaying
project completion based on the project completion date. It can be determined
by subtracting an activity's duration from the late finish (LF - duration). It is equal to the LF of its
predecessor activity..
- Lead
- The time in an activity that allows the successor
activity to start early (prior to the predecessor activity's finish).
- Lessons Learned
- A document used to summarize events that occured during the course of the project. This includes positive as well
as negative experiences and presents better ways to complete similar tasks in the future.
- Loop dependency error
- A circular dependency relationship.
[top]
- Mandatory dependency
- A mandatory cause of a dependency is inherent in the nature of the work; usually
involves physical limitations. Also referred to as hard logic.
- Material
- This cost results when material or equipment required for the project.
- Mitigation strategy
- Organized and coordinated steps to reduce or eliminate a risk by
either decreasing its probability of occurrence or by reducing its impact if it
does occur.
- Milestone
- According to the PMBOK® Guide , it is a significant
event in the project, usually completion of a major deliverable.
- Modified
Internal Rate of Return (MIRR)
- Same as IRR, but assumes returns will be
invested at a rate of return that is different from that of the project.
The financial analysis will assume reinvestment at the Company's
weighted average cost of capital.
[top]
- Net Present Value (NPV)
- A financial analysis technique that
considers the timing of cash flows and the time value of money. Cash flows are
discounted using the Company's cost of capital. Projects with a positive NPV are
considered to add value to the firm. Those with negative NPV diminish value and
should not be pursued.
- Organizational breakdown structure (OBS)
- A depiction of
the project organization arranged so as to relate work packages to
organizational units.
- Outlook
- Also called "Approved Plan". This is the budget
adjusted for approved changes. It supersedes the budget and reflects the current
financial objectives of the Company.
- Out-Of-Plan Project
- A project that is not included in the Outlook.
- Outside Service
- This cost includes bills for vendor services required for the project.
- Overhead
- This cost is often applied as an added
percentage to cover the cost of employee benefits. This percentage may be adjusted each year. The project manager must consult the Accounting
Cost Control Manager for the current percentage and further detail as needed.
[top]
[I]
[J]
[K]
[L]
[M]
[N]
[O]
[A-D]
[E-H]
[P-Q]
[R-Z]
[Home]
|