[A]
[B]
[C]
[D]
[E-H]
[I-O]
[P-Q]
[R-Z]
[Home]
- As late as possible (ALAP) scheduling
- The process of developing a schedule
so that the project will finish as late as possible. Also called just-in-time
(JIT) scheduling.
- As soon as possible (ASAP) scheduling
- The process of developing a schedule from network using early start, early finish, late finish, and float. It will
complete the project as soon as possible.
[top]
- Back loading
- Distributes a larger percent of the budget to the end of an
activity or project rather than toward the start.
- Baseline
- The original approved plan, plus or minus approved scope changes. Usually used with a modifier (e.g., cost baseline, schedule baseline).
- Bottom-up estimating
- Uses detailed tasks in the WBS and rolling up estimates to the top level to arrive at
a project total.
- Budget
- The financial quantification of the operating plan
with which the Company begins each year, and which is approved by the Board of
Directors.
- Business Case
- A document that defines the need or
opportunity, provides financial information, identifies the
justification for doing the project, and includes management approval to
proceed with the Initiating Process.
[top]
- Change control
- The process to manage the revisions to the project scope, time, cost, and quality that occur during the life of the project.
- Closing
- The final of the five processes of project
management that occurs after all deliverables have been produced. During
this process, the project manager performs a post-project review or
audit to evaluate overall project performance. According to the
PMBOK® Guide , closing consists of
formalizing acceptance of the project and bringing it to an orderly end.
- Communications management
- According to the PMBOK® Guide , project
communications management includes the processes required to ensure timely and
appropriate generation, collection, dissemination, storage, and ultimate
disposition of project information.
- Company labor
- This cost results when any
employee charges time to the project.
- Company service
- This cost includes
internal charges from other departments to support the project.
- Completion criteria
- Those things that tell us the project is complete, for example, "all
deliverables finally signed off on by customer," "lessons learned session
complete," etc. The criteria are typically defined by the project manager and
the project team.
- Concurrency
- Two or more activities that can occur during the
same time period but have no relationship to each other.
- Contingency plan
- An alternative strategy that is implemented if a risk event occurs.
- Contingency reserve
- A separate cost for partially planned work. For example rework is
planned although total cost has not been determined. The contingency reserve
would be used for this type of event.
- Controlling
- The fourth of the five processes of project
management. In controlling, the project manager monitors performance,
resources, and budget, supports team members, and removes roadblocks.
The PMBOK® Guide defines this process as ensuring that project
objectives are met by measuring progress and taking corrective action when
necessary.
- Corrective actions
- Changes made to bring expected future performance of the project in line with the plan.
- Cost management
- According to the PMBOK® Guide , project cost
management includes the processes required to ensure that the project is
completed within the approved budget.
- Crashing
- A technique to compress the
critical path by adding overtime, shifts, staff, and subcontractors.
- Critical path
- The longest series of activities in the project
network. The PMBOK® Guide
defines it as the series of activities which determines the earliest
completion of the project.
- Customer
- This role assists the project team in
determining the project objectives and requirements.
[top]
- Deliverables
- The major elements of work of the project.
- Dependencies
- A logical relationship between two project activities or between a project activity and a milestone.
- Discounted payback
- The number of years for the investment to pay for itself based on
discounted cash flows.
- Direct costs
- Expenditures necessary due to the activity itself.
- Discretionary dependency
- A discretionary cause of a dependency is defined by the project team; reflects a desired sequence of activities, not a
mandatory sequence. Also referred preferred logic, preferential logic, or soft logic.
- Documentation library
- see Documentation matrix
- Documentation matrix
- A communication project control tool used to
identify all project document names, the revision date and number, who
is responsible for updating each document, what format the document is
presented and how often a safety backup created.
- Duration
- The business days needed to complete an activity calculated from the start to finish.
- Duration estimate
- The business days needed to complete an
activity. According to the PMBOK® Guide , duration is the number of
work periods likely to be needed to complete each identified activity.
[top]
[A]
[B]
[C]
[D]
[E-H]
[I-O]
[P-Q]
[R-Z]
[Home]
|