[E]
[F]
[G]
[H]
[A-D]
[I-O]
[P-Q]
[R-Z]
[Home]
- Early finish (EF)
- The earliest an activity can finish based on adding the activity's
duration to its early start (ES + duration.).
- Early start (ES)
- The earliest an
activity can start based on the project network.
- Earned value analysis
- A
powerful trend analysis and decision support tool used by many project managers.
- Effort estimate
- The actual amount of effort that is needed to accomplish an
assignment.
- Eighty-hour rule
- A best practice that suggests breaking down the
work until it will take no more than 80 hours of work effort and no less than
eight hours of work effort to accomplish the activity.
- Elapsed time
- The number of calendar days over which an activity occurs between an activity's start and
finish.
- Even loading
- An even distribution of budget over an activity or
project's duration.
- Expense
- This cost includes travel, training, food, and
lodging associated with the project.
- Executing
- The third of the five processes
of project management. During this process, the project manager directs the
resources to carry out the plan and the schedule ensuring all activities are
effectively resourced. According to the PMBOK® Guide, executing consists of
coordinating people and other resources to carry out the plan.
- Executive summary
- A comprehensive restatement of the project's purpose, scope, methods, results,
conclusions, findings and recommendations. The purpose of the executive summary
is to consolidate the principal points of a report or proposal in one place. It
must cover the information in the report in enough detail to accurately reflect
its contents, but concisely enough to permit an executive to digest the
significance of the report without having to read it in full. (Student Handbook:
Spring 1997. EPD 397 Technical Writing Section 308, Steven B. Zwickel,
Instructor.)
[top]
- Fast tracking
- A technique that compresses the critical path by
overlapping activities that would normally be done in sequence, such as design
and construction.
- Float
- The time an activity may be delayed from its early
start without delaying the project completion. It can be determined by
subtracting an activity's early finish from its late finish (LF - EF). This is
also known as slack.
- Finish-to-finish dependency
- According to the PMBOK®
Guide, the predecessor activity must be finished before the successor(s) can
finish.
- Finish-to-start dependency
- According to the PMBOK® Guide, the
predecessor activity must be complete before the successor(s) can start.
- Fixed loading
- The budget is distributed based on fixed points of time over the life
of the activity or project.
- Forecast
- Management's projection or assessment of
how the Company will perform relative to the objectives that are established in
the budget or outlook.
- Front loading
- Distributes more budget at the start of
an activity or project than toward the end.
[top]
- Gantt chart
- A time-scaled
(calendar) bar chart depicting the project's schedule.
- Gap
- see lag
- Hanger
dependency error
- An unintended break in a network path usually caused by
missing activities or missing logical relationships.
- Hard logic
- see mandatory
dependency
- Human resources management
- According to the PMBOK® Guide, project human resource management includes all the
processes required to make the most effective use of people involved
with the project.
[top]
[E]
[F]
[G]
[H]
[A-D]
[I-O]
[P-Q]
[R-Z]
[Home]
|